Nirman Viva-II


Amenities

Children's play area   Well decorated Club House   Club House - Inner   Club House - Outer
     



Construction Status as on 3rd May 2012

Building - D
External Painting Work in Progress

   
  Building - E1
RCC & Brickwork Completed and External
Plaster Work in Final Stage

  



Construction Status as on 2nd April 2012

Building - D
External Painting Work in Progress

   
  Building - E1
RCC & Brickwork Completed and External
Plaster Work in Progress

  



Construction Status as on 1st March 2012

Building - D
RCC & Brickwork Completed and External Plaster Work in Final Stage

  
  Building - E1
RCC Work Completed & 11th Floor Brickwork in Progress

  



Construction Status as on 2nd Feb 2012

Building - D
RCC & Brickwork Completed and External Plaster Work in Final Stage

  
  Building - E1
RCC Work Completed & 10th Floor Brickwork in Progress

  



Construction Status as on 2nd Jan 2012

Building - D
RCC & Brickwork Completed and External Plaster Work in Progress

  
Building - E1
12th Slab in Progress & 9th Floor Brickwork in Progress

  



Construction Status as on 2nd Dec 2011

Building - D
RCC Work Completed & Brickwork Completed

  
Building - E1
11th Slab in Progress & 7th Floor Brickwork in Progress

  



Construction Status as on 1st Nov 2011

Building - D
10th Slab Completed & 8th Floor Brickwork in Progress

  
Building - E1
10th Slab in Progress & 6th Floor Brickwork in Progress

  



Construction Status as on 3rd Oct 2011

Building - D
10th Slab in Progress & 7th Floor Brickwork Completed

  
Building - E1
9th Slab in Progress & 5th Floor Brickwork Completed

  



Construction Status as on 1st Sept 2011

Building - D
9th Slab in Completed & 5th Floor Brickwork in Progress

  
Building - E1
8th Slab in Progress & 4th Floor Brickwork in Progress

  



Construction Status as on 1st Aug 2011

Building - D
8th Slab in Completed & 3rd Floor Brickwork Completed

  
Building - E1
7th Slab in Progress & 3rd Floor Brickwork Completed

  



Construction Status as on 1st July 2011

Building - D -
7th Slab in Progress & 2nd Floor Brickwork Completed

  
Building - E1
6th Slab in Progress & 2nd Floor Brickwork Completed

  



Construction Status as on 1st June 2011

Building - D
6th Slab in progress

  
Building - E1
5th Slab & Brickwork of 1st floor in progress

  



Construction Status as on 1st May 2011

Building - D -
4th Slab & Brickwork of 1st floor in progress

  
Building - E1
3rd Slab Completed & 4th slab in progress

  